FINISHING COMMISSIONING -
APPLIANCE
1 Locate edge of front panel (A) onto the
supporting ledge (B) on the baseplate.
Refit securing screws (C) to secure.
2Slide control box (D) into boiler.
Secure with screws (E).
Locate the ball stud connectors (F) and
push-fit upper front panel (G) towards the
boiler to secure.
3Locate the top panel (H) onto the ball stud
connections ( J ) and press down to secure.
Always apply pressure at the edges of
the boiler panels when securing to avoid
accidental damage.
Handover:
Complete the Guarantee Registration Card,
Combustion Record (at the rear of this
manual) and CD11 or an equivalent
commissioning form.
Set up the controls and show the user how
to operate all the controls shown in the User
Guide and all system controls.
Where applicable, instruct the customer how
to repressurise the system.
If the appliance is unused and exposed to
freezing conditions, shut off all the mains
supplies, isolate the boiler and drain the
system and boiler including the secondary
heat exchanger.
NOTE: Release drain point (K) to drain the
secondary heat exchanger.
FINISHING COMMISSIONING -
APPLIANCE
INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER GREENSTAR UTILITY 32/50 & 50/708 716
109 711B 07.2010
38
COMMISSIONING