INSTALLATION, COMMISSIONING AND SERVICING
INSTRUCTIONS
WALL HUNG RSF GAS FIRED CONDENSING BOILER
GREENSTAR i SYSTEM
6720643356-00 1Wo
FOR SEALED CENTRAL HEATING SYSTEMS AND INDIRECTLY
FED DOMESTIC HOT WATER
6720644743b (2011/08)
The appliance is for use with Natural Gas or
L.P.G. (Cat II 2H3P type C13, C33 & C53)
Model GC Number
Natural Gas 12i System 41-311-67
15i System
41-311-84
18i System 41-311-86
24i System 41-311-68
Liquid Petroleum Gas 12i System 41-311-69
15i System
41-311-85
18i System
41-311-87
24i System 41-311-70
Page view 0
1 2 3 4 5 6 ... 71 72

Summary of Contents

Page 1 - GREENSTAR i SYSTEM

UK/IEINSTALLATION, COMMISSIONING AND SERVICING INSTRUCTIONSWALL HUNG RSF GAS FIRED CONDENSING BOILERGREENSTAR i SYSTEM6720643356-00 1WoFOR SEALED CENT

Page 2 - CONTENTS

APPLIANCE INFORMATION6 720 644 743b (2011/08)10Fig. 3 Additional components1 Burner ON indicator light (green) 9 PRV pipe connection point2 Power ON/O

Page 3 - 1.1 EXPLANATION OF SYMBOLS

PRE-INSTALLATION6 720 644 743b (2011/08)113 PRE-INSTALLATION3.1 CLEANING PRIMARY SYSTEMSBEFORE CLEANING THE SYSTEM:B Ensure that the system and pipe w

Page 4 - 1.2 SAFETY PRECAUTIONS

PRE-INSTALLATION6 720 644 743b (2011/08)123.2 MAINS SUPPLY3.2.1 ELECTRICAL SUPPLY• Supply: 230V - 50 Hz, 140 Watts• Cable: PVC insulated 0.75 mm2 (24

Page 5

PRE-INSTALLATION6 720 644 743b (2011/08)133.3 WATER SYSTEM AND PIPE WORKPLASTIC PIPE WORK:• Any plastic pipe work must have a polymeric barrier with 6

Page 6 - 2APPLIANCE INFORMATION

PRE-INSTALLATION6 720 644 743b (2011/08)14EXISTING BUILDS: S AND Y PLAN SYSTEMS:S PLAN LAYOUTFig. 6 Existing build - S PlanY PLAN LAYOUTWITH EXTERNAL

Page 7 - 2.2 TECHNICAL DATA

PRE-INSTALLATION6 720 644 743b (2011/08)153.4 CONDENSATE PIPE WORK3.4.1 INTERNAL CONNECTIONSIn order to minimise risk of freezing during prolonged col

Page 8 - 2.3 LAYOUT

PRE-INSTALLATION6 720 644 743b (2011/08)163.4.2 EXTERNAL CONNECTIONSIf no other discharge method is possible then the use of an externally run condens

Page 9

PRE-INSTALLATION6 720 644 743b (2011/08)17CONDENSATE SOAK AWAY• The condensate drainage pipe may be run above or below the ground to the soak away. Th

Page 10 - 6 720 644 743b (2011/08)

PRE-INSTALLATION6 720 644 743b (2011/08)183.6 BOILER LOCATION AND CLEARANCES3.6.1 INSTALLATIONThis boiler is only suitable for installing internally w

Page 11 - 3 PRE-INSTALLATION

PRE-INSTALLATION6 720 644 743b (2011/08)193.6.5 BOILER CLEARANCES - UNVENTILATED COMPARTMENTS3.6.6 INSTALLATION CLEARANCES - UNVENTILATED COMPARTMENTS

Page 12 - 3.2 MAINS SUPPLY

CONTENTS6 720 644 743b (2011/08)2CONTENTS1 KEY TO SYMBOLS AND SAFETY PRECAUTIONS 31.1 Explanation of symbols . . . . . . . . . . . . . . 31.2 Safety

Page 13

PRE-INSTALLATION6 720 644 743b (2011/08)203.7 PLUMBING MANIFOLD3.7.1 CONNECTIONSUse the fittings supplied in the Hardware literature pack.• If the boi

Page 14

PRE-INSTALLATION6 720 644 743b (2011/08)213.8 FLUE OPTIONS FLUE LENGTHSThe flue systems have different maximum flue lengthsThe Greenstar series has th

Page 15 - 3.4 CONDENSATE PIPE WORK

PRE-INSTALLATION6 720 644 743b (2011/08)22350 mm 570 mm130 mm MinFlat roof300 mm500 mmPitchedroof234561098716720643895-12.1Wo

Page 16

PRE-INSTALLATION6 720 644 743b (2011/08)233.9 FLUE TERMINAL POSITIONSFig. 22 Flue terminal positionsKey to illustration1. Flue clearance must be at le

Page 17 - 3.5 PRESSURE RELIEF PIPE WORK

PRE-INSTALLATION6 720 644 743b (2011/08)243.10 PLUME MANAGEMENT TERMINAL POSITIONSFig. 23 Plume terminal positionsKey to illustration1. 600 mm distanc

Page 18

INSTALLATION6 720 644 743b (2011/08)254INSTALLATION4.1 UNPACKING THE WALL FRAME AND ANCILLARY ITEMS1. Wall mounting frame2. Wall mounting template3. I

Page 19

INSTALLATION6 720 644 743b (2011/08)264.2 WALL MOUNTING TEMPLATE & FLUE OPENINGSAFETY:All relevant safety precautions must be undertaken. Protecti

Page 20 - 3.7 PLUMBING MANIFOLD

INSTALLATION6 720 644 743b (2011/08)274.3 UNPACKING THE APPLIANCE1. Outer carton2. Inner sleeve (unwrap from front)3. Packing base4. Protective wrappi

Page 21 - 3.8 FLUE OPTIONS

INSTALLATION6 720 644 743b (2011/08)284.4 BOILER CONNECTIONSGAS AND WATER CONNECTIONSB Remove wall mounting template and secure the wall mounting fram

Page 22 - PRE-INSTALLATION

INSTALLATION6 720 644 743b (2011/08)29HANGING THE BOILERB Hang the boiler on to the wall mounting frame by the two brackets positioned left and right

Page 23 - 3.9 FLUE TERMINAL POSITIONS

KEY TO SYMBOLS AND SAFETY PRECAUTIONS6 720 644 743b (2011/08)31 KEY TO SYMBOLS AND SAFETY PRECAUTIONS1.1 EXPLANATION OF SYMBOLSWARNING SYMBOLSSignal w

Page 24

INSTALLATION6 720 644 743b (2011/08)304.5 FLUE INSTALLATIONHORIZONTAL FLUE (60/100mm diameter)For vertical flues and 80/125mm horizontal flues, please

Page 25 - 4INSTALLATION

INSTALLATION6 720 644 743b (2011/08)314.5.3 INSTALLING THE TELESCOPIC FLUE:Refer to figure 41.1. Set the flue length to the distance required, secure

Page 26

INSTALLATION6 720 644 743b (2011/08)324.5.4 FLUE TERMINAL PLUME RE-DIRECTIONThe flue discharge can be re-directed allowing some plume redirection cont

Page 27 - 4.3 UNPACKING THE APPLIANCE

INSTALLATION6 720 644 743b (2011/08)334.6 CONDENSATE CONNECTIONNever terminate or discharge into any open source, including; sink, bath, shower, bidet

Page 28 - 4.4 BOILER CONNECTIONS

INSTALLATION6 720 644 743b (2011/08)344.7 ELECTRICAL• The mains electrical supply to the boiler must be through either a fused double pole isolator or

Page 29

INSTALLATION6 720 644 743b (2011/08)35NEW COMPLETE SYSTEM INSTALLATIONSIf a new complete heating system is installed in a new build property or it is

Page 30 - 4.5 FLUE INSTALLATION

COMMISSIONING6 720 644 743b (2011/08)365 COMMISSIONING5.1 PRE-COMMISSIONING CHECKSCheck that the service and water pipes are connected to the correct

Page 31

COMMISSIONING6 720 644 743b (2011/08)375.2 FILLING THE SYSTEM1. Turn on the water main and open the system valves.2. Open all radiator valves.3. Fill

Page 32

COMMISSIONING6 720 644 743b (2011/08)385.4 STARTING THE APPLIANCEFig. 61 Control panelSwitching the appliance on/off:B Turn on mains power supply, the

Page 33 - 4.6 CONDENSATE CONNECTION

COMMISSIONING6 720 644 743b (2011/08)395.5 COMMISSIONINGHaving checked:B That the boiler has been installed in accordance with the installation instru

Page 34 - 4.7 ELECTRICAL

KEY TO SYMBOLS AND SAFETY PRECAUTIONS6 720 644 743b (2011/08)41.2 SAFETY PRECAUTIONSIF YOU SMELL GAS:B CALL NATIONAL GAS EMERGENCY SERVICE ON 0800 11

Page 35

COMMISSIONING6 720 644 743b (2011/08)405.5.2 CHECKING THE GAS RATEB The gas rate should be measured at the gas meter after 10 minutes operation at max

Page 36 - 5 COMMISSIONING

COMMISSIONING6 720 644 743b (2011/08)415.6 FINISHING COMMISSIONING5.6.1 REPLACE OUTER CASING:B Replace outer casing making sure that the securing poin

Page 37 - 5.3 WATER TREATMENT

SERVICE AND SPARES6 720 644 743b (2011/08)426SERVICE AND SPARES6.1 INSPECTION AND SERVICE• To ensure the continued efficient operation of the applianc

Page 38 - 5.4 STARTING THE APPLIANCE

SERVICE AND SPARES6 720 644 743b (2011/08)436.2 CHECK THE GAS INLET PRESSURERefer to section 5.5.1 for more informationB Check the gas supply working

Page 39 - 5.5 COMMISSIONING

SERVICE AND SPARES6 720 644 743b (2011/08)446.4 FAN PRESSURE TESTSETTING THE BOILER TO MAXIMUM1. Press and HOLD service button for more than 10 second

Page 40

SERVICE AND SPARES6 720 644 743b (2011/08)456.5 FLUE GAS ANALYSISCOMBUSTION TEST:B Connect the flue gas analyser to the flue gas sampling point as sho

Page 41 - 5.6 FINISHING COMMISSIONING

SERVICE AND SPARES6 720 644 743b (2011/08)466.6 SETTING THE AIR/GAS RATIO6.6.1 SETTING THE CO/CO2B Refer to section 5.6.1 and ensure that the gas inle

Page 42 - 6SERVICE AND SPARES

SERVICE AND SPARES6 720 644 743b (2011/08)476.7 CLEANING THE HEAT EXCHANGERB Isolate the power to the appliance and remove outer case and base panel.1

Page 43 - 6.3 CHECKING FLUE INTEGRITY

SERVICE AND SPARES6 720 644 743b (2011/08)48BURNER REMOVALRefer to figure 831. Remove clamping plate.2. Remove spark/flame electrode assembly and seal

Page 44 - 6.4 FAN PRESSURE TEST

SERVICE AND SPARES6 720 644 743b (2011/08)49ACCESS COVER REMOVALRefer to figure 85.1. Remove the two pozi-drive screws 2. Remove the access cover3. Re

Page 45 - 6.5 FLUE GAS ANALYSIS

KEY TO SYMBOLS AND SAFETY PRECAUTIONS6 720 644 743b (2011/08)5British Standards:Where no specific instruction is given, reference should be made to th

Page 46 - 6.6 SETTING THE AIR/GAS RATIO

SERVICE AND SPARES6 720 644 743b (2011/08)506.8 REPLACEMENT OF PARTS6.8.1 REMOVING OUTER CASE1. Undo the two screws securing the top of the boiler cas

Page 47

SERVICE AND SPARES6 720 644 743b (2011/08)516.8.4 FLUE OVERHEAT THERMOSTAT(WITH GROMMET)To remove and replace the thermostat either:B Using a small te

Page 48

SERVICE AND SPARES6 720 644 743b (2011/08)526.8.6 GAS VALVERefer to figure 92B Isolate gas supply at boiler gas cock.1. Remove wire clip from the gas

Page 49

SERVICE AND SPARES6 720 644 743b (2011/08)53B Rotate fan and air/gas manifold assembly (1.) around the top of the heat exchanger until the lug on the

Page 50 - 6.8 REPLACEMENT OF PARTS

SERVICE AND SPARES6 720 644 743b (2011/08)546.8.9 ELECTRODE ASSEMBLY AND BURNERRefer to figure 98.B Disconnect spark electrodes and flame sensor conne

Page 51 - 6720643895-70.1Wo

SERVICE AND SPARES6 720 644 743b (2011/08)55Refer to figure 101.1. Release the clip.2. Move the lower exhaust connector upB Remove the complete exhaus

Page 52

SERVICE AND SPARES6 720 644 743b (2011/08)566.8.11 ACCESS TO BOILER CONTROL COMPONENTS1. Remove three screws.2. Remove cover from control.Fig. 104 Rem

Page 53

SERVICE AND SPARES6 720 644 743b (2011/08)576.8.14 REPLACING CONTROLSRefer to figure 108.1. Remove ALL electrical connections from the control PCB inc

Page 54

SERVICE AND SPARES6 720 644 743b (2011/08)586.8.15 SYPHON REMOVALTo release the syphon from the sump:1. Disconnect the discharge hose from the condens

Page 55

SERVICE AND SPARES6 720 644 743b (2011/08)596.8.18 AUTO AIR VENTB Ensure the appliance has been fully drained.B Use a screwdriver or similar to rotate

Page 56

APPLIANCE INFORMATION6 720 644 743b (2011/08)62APPLIANCE INFORMATION2.1 APPLIANCE2435* 710mm to top of case front1700mm*400mm330mmDepth to wall (When

Page 57 - 6720643895-78.1Wo

SERVICE AND SPARES6 720 644 743b (2011/08)606.8.21 PRESSURE GAUGEB Refer to figure 117B Ensure the appliance has been fully drained.3. Prise the lugs

Page 58

SERVICE AND SPARES6 720 644 743b (2011/08)616.8.23 CH PRESSURE RELIEF VALVEB Remove the hydraulic block from the boiler (See Removing the Hydraulic Bl

Page 59

SERVICE AND SPARES6 720 644 743b (2011/08)62Expansion vessel replacement (Removing the Boiler)B Isolate electrical supply.B Isolate system and gas con

Page 60

SERVICE AND SPARES6 720 644 743b (2011/08)636.9 SHORT PARTS LISTFan8 716 116 067 0GC No. H26 536Burner8 718 120 619 0GC No. H26 538Gas Valve8 716 111

Page 61

FAULT FINDING AND DIAGNOSIS6 720 644 743b (2011/08)647 FAULT FINDING AND DIAGNOSIS7.1 FAULT FINDINGThe electronic control system for this boiler incor

Page 62

FAULT FINDING AND DIAGNOSIS6 720 644 743b (2011/08)65Slow flash (mostly off, flashes on)Flashing (reset required)Ignition lockout B Gas present and at

Page 63 - 6.9 SHORT PARTS LIST

FAULT FINDING AND DIAGNOSIS6 720 644 743b (2011/08)667.1.1 CIRCUIT DIAGRAMFANFSFR NP LPLNSNLSLRST8ST9ST17ST18ST5 ST4ST10EarthMAINSSUPPLYPUMPSUPPLYSPAR

Page 64 - 7 FAULT FINDING AND DIAGNOSIS

FAULT FINDING AND DIAGNOSIS6 720 644 743b (2011/08)677.2 BOILER FUNCTIONFig. 124 Boiler functionNOYESMAINSPOWERSUPPLYONBOILERDEMANDFan tostartspeed.Pu

Page 65

FAULT FINDING AND DIAGNOSIS6 720 644 743b (2011/08)687.3 PROTECTION FUNCTIONFig. 125 Protection functionInternal boilertemperaturebetween8°C & 5°C

Page 66 - Neutral = brown

6 720 644 743b (2011/08)69NOTES

Page 67 - IGNITION SEQUENCE

APPLIANCE INFORMATION6 720 644 743b (2011/08)72.2 TECHNICAL DATADESCRIPTION NATURAL GAS LPGUNIT 12i 15i 18i 24i 12i 15i 18i 24iGas flow rate - Max. 10

Page 68 - 7.3 PROTECTION FUNCTION

Service RecordIt is recommended that your heating system is serviced regularly and that the appropriate Service Interval Record is completed.Service P

Page 69

Failure to install and commission according to the manufacturer’s instructions and complete this Benchmark Commissioning Checklist will invalidate the

Page 70 - Service Record

Worcester, Bosch GroupCotswold Way, Warndon, Worcester WR4 9SW.Tel. 0844 892 9900Worcester, Bosch Group is a brand name of Bosch Thermotechnology Ltd.

Page 71 - CONDENSING BOILERS ONLY

APPLIANCE INFORMATION6 720 644 743b (2011/08)82.3 LAYOUTFig. 1 Main boiler components6720644743-02.1Wo123130292827261014121113151625232422212019181734

Page 72

APPLIANCE INFORMATION6 720 644 743b (2011/08)9Fig. 2 Hydraulic block components1Expansion Vessel 23 Hydraulic block mounting plate2 Sensor - Boiler fl