9.1 The appliance is suitable for connection to all conventional indi-
rect hot water systems utilising an indirect double feed cylinder.
9.2 The flow and return connections are located at the rear of
the appliance.
9.3 There is no requirement for a system bypass.
9.4 The pressure jet burner fitted to the appliance has full
automatic control and hence there is no requirement for heat
leak radiators.
9.5 The primary system should be flushed and treated in
accordance with the recommendations of BS 7593:1992 before
the system is handed over to the user.
9.6 The pump should be set in accordance with the heating load
requirements to give a flow and return differential temperature
of 11°C under full load conditions.
Open Vent Primary System.
(See Fig.17).
The following points are for guidance only. The system
installation should be carried out in accordance with BS 5449:
Part 1.
1.
System Pipework
The first metre of pipework from all appliance connections must
be in copper; afterwards copper or plastic pipe can be used. The
plastic pipe must be manufactured to BS 7291 and installed to
BS 5955 part 8. It is important to protect the system
components; the plastic pipe specified must be resistant to the
ingress of oxygen.
2. Feed and Expansion System
The feed and expansion pipes must rise continuously from the
appliance and must be of the minimum diameter shown in Fig 17.
The cistern must be arranged to provide a minimum static head
of 1 metre above the top of the highest point in the heating
circuit.
3. Filling and Venting
Air in the appliance is expelled through the vent pipe or
dissipated into the system. Manual air vents should be fitted at
any high points in the system.
There is a connection on the appliance for connecting an auto
air vent.
Sealed Primary System
The appliance is supplied with a manual reset thermostat and is
suitable for use with a sealed primary system.
General
The system should be installed in compliance with the
9. Heating and Hot Water System
13
Fig. 19. System filling and make-up
Heating
return
Non return
valve
Stop
cock
Auto air
vent
Fill point.
Heating return
30mm (12in) min.
above highest
point of the system
Make up
vessel
Method 1 Method 2