32 | Installation
6 720 644 143 (2010/09)
6.6 Checking the connections
Water connections
B Open the heating flow and return valves and fill the
heating system.
B Check sealing points for leaks (testing pressure:
max. 2.5 bar (250 kPA) at the pressure gauge).
B Open the cold water valve on the appliance and a turn
on a hot water tap until water runs out. Max pressure:
10 bar (1000 kPA).
Gas supply pipe
B Close the gas valve to protect the gas valve from
pressure damage.
B Check sealing points for leaks.
B Release the pressure on the gas supply pipe.