COMMISSIONING SERVICING
FILLING
It is important that the inner cylinder is pressurized first, followed
by the primary circuit.
Check the pressure in the DHW expansion vessel is 3 bar
(44PSI), i.e the same as the setting of the pressure reducing valve.
Before filling, open the hot tap furthest away from the
Greenstore cylinder to let air out. Open the cold main isolation
valve and allow the unit to fill.
When water flows from the tap, allow it to run for a short while
to flush through any dirt, swarf or flux residue.
Close the tap and open every other hot tap in turn to purge all
remaining air.
The primary circuit can now be filled.
PRIMARY CIRCUIT - INDIRECT UNITS
Consult the Worcester Bosch commissioning instructions and fill
the primary circuit.
STORAGE TEMPERATURE
In many applications the guidance on Legionella control and safe
water delivery temperatures will require storing the water at 60-
65°C, distributing at 50-55°C and using thermostatic mixing valves
to control the final temperature.
SAFETY VALVE CHECKS
In order to check correct operation of both the expansion and
temperature/pressure relief valves, fully open them allowing as
much water as possible to flow through the tundish. Check that the
discharge pipework is free from debris and is carrying the water
away, to waste, efficiently. Release the valves and check that they
reseat properly.
During heat-up of the cylinder there should have been no sign
of water discharge from either the expansion relief valve or the
temperature / pressure relief valve.
SPARE PARTS
Worcester carry the full range of spares listed below in stock.
If you order before noon we will dispatch the same day
for delivery the next day to most locations.
8 716 113 407 0 - Inlet control set (pressure reducing valve,
strainer and expansion relief valve )
8 716 113 409 0 - Tundish
8 716 113 416 0 - 19 litre Expansion Vessel
8 716 113 418 0 - 24 litre Expansion Vessel
8 716 113 415 0 - Bracket, Expansion Vessel
8 716 113 414 0 - Hose, Expansion Vessel ( 3/4” M x 3/4” F )
8 716 113 439 0 - Allen Key
8 716 113 440 0 - Olive, Blanking 22mm
8 716 113 441 0 - Olive, Blanking 15mm
8 716 113 442 0 - Washer
8 716 113 498 0 - Solar High Limit Stat
8 716 113 473 0 - Temperature/Pressure relief valve
8 716 112 318 0 - Hot water sensor GT3
SERVICING
GENERAL
Servicing should only be carried out by competent installers
and any spare parts used must be purchased from Worcester.
NEVER bypass any safety devices or operate the unit without
them being fully operational.
WARNING:
WATER DRAINED OFF MAY BE VERY HOT!
DRAINING
Isolate the unit from the cold mains.
Open a hot water tap at the lowest position in the building, to
reduce the pressure.
Remove the mains water inlet connection. Attach a flexible hose to
the connection on top of the cylinder, ensuring the hose reaches to
a level well below the unit (The greater the difference in elevation,
the greater the flow rate and the maximum amount of water drained
from the cylinder).
Disconnect the hot water outlet.
Start the siphon effect, by either sucking or pumping the drain side
of the flexible hose.
Allow the cylinder to drain completely.
FLUSHING THE TANK
To flush the cylinder, follow the procedure for draining. Connect a
hose to the hot water outlet and then flush the system.
WARNING:
POSSIBLE SCALDING!
ANNUAL MAINTENANCE
Greenstore cylinders require an annual service in order to
ensure safe working and optimum performance.
It is essential that the following checks are performed by a
competent installer on an annual basis. This is done at the same
time as the annual heat pump and solar service.
1) Twist the cap of the expansion relief valve on the inlet
control set and allow water to flow for 5 seconds. Release
and make sure it resets correctly. Repeat with the pressure
/ temperature relief valve.
In both cases check that the discharge pipework is carrying the
water away adequately. If not check for blockages etc. and
clear.
2) Check the pressure in the DHW expansion vessel is charged to
3 bar. Turn off the water supply to the unit and open a hot tap
first.
3) Unscrew the head on the inlet control set and clean the
mesh filter within.
4) The benchmark log book, in the back of this manual, must be
updated at each service.
YOUR GUARANTEE MAY BE VOID WITHOUT
PROOF OF ANNUAL SERVICING
6 COMMISSIONING AND SERVICING
Worcester Bosch Greenstore
THE GUARANTEE
The Greenstore cylinder carries a 2 year guarantee against faulty
materials or manufacture provided that:
• It has been correctly installed as per this document and all the
relevant standards, regulations and codes of practice in force at
the time.
• It has not been modified in any way.
• It has not been misused, tampered with or subjected to neglect
• It has only been used for the storage of potable water.
• It has not been subjected to frost damage.
The unit has been serviced annually
• The benchmark log book has been filled in after each annual service
• The guarantee provided starts from the date of commissioning
• Building Control notification is required
Please note that invoices for servicing may be requested to prove
that the unit has been serviced annually.
All the components fitted to / or supplied with the Greenstore
cylinder carry a 2 year guarantee.